2010年P(guān)MP美國項目管理考試習(xí)題及答案22
QUEST To calculate the expected value of an outcome:
A divide the value of each outcome by its probability, then add the results.
B divide the value of the desired outcome by the value all possible outcomes
C multiply the value of each outcome by its probability, then add the results
D use linear regression to assess the expected value of the outcome
E B and D only
參考答案:C
QUEST Which of the following is most closely associated with pure risk:
A profit and loss
B personnel turnover
C insurance
D market fluctuations
E A and D only
參考答案:C
QUEST Which of the following is most closely associated with business risk:
A profit and loss
B personnel turnover
C workmen's compensation
D liability insurance
E All of the above.
參考答案:A
QUEST It is useful to conduct project risk assessment according to the project's
A charter
B statement of work
C Work Breakdown structure
D network
E budget
參考答案:C
QUEST Uncertainty refers to a situation where:
A the outcomes are known but their probabilities are high
B the outcomes and their probabilities are known
C neither the outcomes nor their probabilities are known
D states of nature can change at any time
E probabilities of various states of nature can change at any time
參考答案:C