PMP美國項目管理認證考試的模擬題精選10
A change control system should include all the following except-
a. Procedures for automatic approval of defined categories of change
b. Paperwork, tracking systems, and approval levels necessary for authorizing changes
c. A description of the powers and responsibilities of the change control board
d. Procedures for conducting a midproject control system review
Qustions 3:
Two fundamental objectives of project control are to--
a. Alter activities to achieve results and manage organizational assets
b. Eliminate unexpected technical problems and identify technical difficulties that require more resources
c. Ensure that resources are available when needed and avoid increases in the scope of work
d. Have the required material, personnel, and equipment available when needed and ensure that budgeting is adequate
Qustions 5:
The project plan is important in change control because it--
a. Provides the baseline against which changes are managed
b. Provides the information on project performance
c. Alerts the project team to issues that may cause problems in the future
d. Is expected to change throughout the project
Qustions 2:
Written changes orders should be required on --
a. All projects, large and small
b. Large projects
c. Projects with a formal configuration management system in place
d. Projects for which the cost of a change control system can be justified
Qustions 4:
The principal sources of project failure are-
a. Lack of a projectized or strong matrix structure, poor scope definition, and lack of a project plan
b. Lack of commitment or support by top management, disharmony on the project team, and lack of leadership by the project manager
c. Poorly identified customer needs, a geographically dispersed project team, and little communication with the customer until the project is delivered
d. Organizational factors, poorly identified customer needs, inadequately specified project requirements, and poor planning and control
Qustions 6:
Interface management is --
a. Considered to be one of the easier aspects of implementing the project plan
b. Primarily concerned with the technical issues associated with linking system components in a configuration
c. Facilitated by use of the WBS to display the ways people on the project interact and their duties and responsibilities
d. The process of coordinating the various elements of the project so that they meet their joint goals of performance, schedule, and budget
本站推薦
- 1PMP項目管理進度系統(tǒng),能否讓您的項目一馬當先?答案當然是肯定的!
- 2項目進度管理有難題?PMP系統(tǒng):一問就知,輕松解決
- 3PMP項目管理,項目進度管理的疑問終結(jié)者,您還在等什么?
- 4項目進度難掌控?PMP管理系統(tǒng):疑問解答,效率倍增!
- 5PMP項目管理進度系統(tǒng),能否讓您的項目效率翻倍?答案就在這里!
- 6項目進度滯后?PMP管理系統(tǒng):一問就知道怎么加速!
- 7項目管理不再迷茫,PMP進度系統(tǒng):您的疑問我來答
- 8PMP在手,項目進度管理難題還用問嗎?輕松搞定
- 9還在為項目進度頭疼?PMP管理系統(tǒng)幫您一問解千愁!