PMP認(rèn)證考試練習(xí)題(二十)(中英文)
申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114
1. In making key changes to a project, it is important to have a formal change process and a ____________ responsible for approving or rejecting requests.
Stakeholder
Change control board
Subject matter expert
Project manager
在項(xiàng)目做出重要變更時(shí),重要的是要有一個(gè)正式的變更過程和一個(gè)負(fù)責(zé)批準(zhǔn)或拒絕變更要求的 :
項(xiàng)目相關(guān)者
變更控制委員會(huì)
領(lǐng)域事務(wù)專家
項(xiàng)目經(jīng)理
2.In which project life cycle phase are the risks associated with project integration usually the smallest?
Project initiation and approval
Project planning
Project execution
Project closeout
在項(xiàng)目生命周期哪一階段,項(xiàng)目整合的風(fēng)險(xiǎn)最???.
項(xiàng)目立項(xiàng)和審定
項(xiàng)目規(guī)劃
項(xiàng)目執(zhí)行
項(xiàng)目收尾

3.The most encompassing document to help the project team with project integration activities is the _________.
Project charter
Project plan
“As built” report
Scope change control procedure
能幫助項(xiàng)目團(tuán)隊(duì)進(jìn)行項(xiàng)目整合活動(dòng)的最完整的文件是:
項(xiàng)目章程
項(xiàng)目計(jì)劃
進(jìn)程報(bào)告
范圍變更控制流程
4. Prevention costs include all of the following, except:
Training
Supplier certification
Design reviews
Defect evaluation
預(yù)防成本包括所有下列事項(xiàng),除了:
培訓(xùn)
供應(yīng)商合格書
設(shè)計(jì)評(píng)審
缺陷評(píng)估
5. For the following group of numbers: 80, 10, 10, 50, 70 and 90, what is the standard deviation?
10
80
35
60
對(duì)于后面這組數(shù): 80,10,10,50,70 和 90,標(biāo)準(zhǔn)差是什么?
10
80
35
60
6. If a company wants to measure up to the Malcolm Baldrige National Quality Award, which of the following criteria will they be evaluated to?
ISO 9000
Quality policy
Strategic planning
ANSI standards
如果一家公司想要達(dá)到獲得Malcolm Baldrige國(guó)家質(zhì)量獎(jiǎng), 下列哪一標(biāo)準(zhǔn)將會(huì)是他們要進(jìn)行評(píng)估的?
ISO 9000
質(zhì)量方針
戰(zhàn)略規(guī)劃
ANSI標(biāo)準(zhǔn)
7. When a process control chart is set up optimally, the upper and lower specification limits typically are:
Set equal to the upper and lower control limits
Set outside the upper and lower control limits
Set inside the upper and lower control limits
Set at two sigma from the mean value
當(dāng)一個(gè)過程控制圖表被很理想建立完成時(shí), 其規(guī)格要求的上限和下限通常是:
設(shè)定等于控制范圍的上限和下限
設(shè)在控制范圍的上限和下限之外
設(shè)在控制范圍的上限和下限之內(nèi)
設(shè)在均值的二個(gè)西格瑪sigma 水平
本站推薦
- 1PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目一馬當(dāng)先?答案當(dāng)然是肯定的!
- 2項(xiàng)目進(jìn)度管理有難題?PMP系統(tǒng):一問就知,輕松解決
- 3PMP項(xiàng)目管理,項(xiàng)目進(jìn)度管理的疑問終結(jié)者,您還在等什么?
- 4項(xiàng)目進(jìn)度難掌控?PMP管理系統(tǒng):疑問解答,效率倍增!
- 5PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目效率翻倍?答案就在這里!
- 6項(xiàng)目進(jìn)度滯后?PMP管理系統(tǒng):一問就知道怎么加速!
- 7項(xiàng)目管理不再迷茫,PMP進(jìn)度系統(tǒng):您的疑問我來答
- 8PMP在手,項(xiàng)目進(jìn)度管理難題還用問嗎?輕松搞定
- 9還在為項(xiàng)目進(jìn)度頭疼?PMP管理系統(tǒng)幫您一問解千愁!