PMP認(rèn)證考試練習(xí)題及參考答案(十九)
1. history has shown that project managers can be trained in a combination of ways. which method is usually
preferred by most companies?
a. experiential learning, on-the-job
b. formal education and special course (degreed programs)
c. professional activities, seminars
d. individual readings
e. none of the above考試大(www.Examda。com)
ans: a
2. the purpose of configuration management is to:
a. insure drawings are updated
b. control change throughout the project
c. control change during the production only
d. generate engineering change proposals
e. inform the project manager of changes
ans: b
3. three types of written media used in organizations are _____, _____, and ______.
a. manual, letters, guidelines
b. individually-oriented, legally-oriented, organizationally oriented
c. guidelines, forms, procedures
d. letters, guidelines, brochures來源:考試大
e. letters, contracts, policies.
ans: d
4. which of the following is considered a direct cost for producing a widget?
a. the cost of the materials used to produce a widget.
b. the labor costs of the workers who actually produced the widget.
c. the rent for the building in which the widget was manufactured
d. the salary of senior management and the project sponsor
e. a and b only
ans: e
5. _____ best describes the goal of a project in its relationship with the customer, from initial contact
through delivery.
a. fitness for use
b. customer satisfaction
c. conformance to requirements
d. fitness for purpose
e. all of the above.來源:考試大網(wǎng)
ans: b
6. a communicator can present information using the following media except:
a. visual
b. audio
c. tactile
d. performal
e. both a and b
ans: d
7. advantages of the functional (hierarchical) form of organization include _____ and creation of technical
competence.
a. ease of horizontal coordination
b. clearly defined authority
c. high information processing capability
d. single voice to customers
ans: b來源:www.examda.com
8. quality and _____ are directly related.
a. productivity
b. cost overruns
c. scope control
d. pareto diagram
e. none of the above.
ans: a
9. resource leveling will often affect the project by making it:
a. shorter.
b. longer
c. more responsive to customer needs.
d. a and c
e. b and c.
ans: b來源:考試大
10. selection criteria for project selection include:
a. cost versus benefit
b. risk
c. contribution towards organizational goals
d. rate of return
e. all of the above.
ans: e
11. the statement of work (sow) is developed during the _____ cycle.
a. award
b. solicitations
c. requirementswww.Examda.CoM
d. contractual
e. requisitions
ans: c
12. which of the following depreciation methods provides for accelerated depreciation of an asset:
a. double declining balance.
b. straight line.
c. exponential depreciation
d. double sum of the years digits
e. double increasing balance
ans: a
本站推薦
- 1PMP項目管理進度系統(tǒng),能否讓您的項目一馬當(dāng)先?答案當(dāng)然是肯定的!
- 2項目進度管理有難題?PMP系統(tǒng):一問就知,輕松解決
- 3PMP項目管理,項目進度管理的疑問終結(jié)者,您還在等什么?
- 4項目進度難掌控?PMP管理系統(tǒng):疑問解答,效率倍增!
- 5PMP項目管理進度系統(tǒng),能否讓您的項目效率翻倍?答案就在這里!
- 6項目進度滯后?PMP管理系統(tǒng):一問就知道怎么加速!
- 7項目管理不再迷茫,PMP進度系統(tǒng):您的疑問我來答
- 8PMP在手,項目進度管理難題還用問嗎?輕松搞定
- 9還在為項目進度頭疼?PMP管理系統(tǒng)幫您一問解千愁!