PMP認(rèn)證考試練習(xí)題及參考答案(十三)
1. of the following, who has the ultimate responsibility for meeting project quality objectives?
a. project engineer
b. project manager
c. functional manager
d. quality assurance manager
e. project owner
ans: bhttp://ks.examda.com
2. risk mitigation involves all but which of the following:
a. developing system standards (policies, procedure, responsibility standards)
b. obtaining insurance against loss
c. identification of project risks
d. performing contingent planning
e. developing planning alternatives
ans: c
3. the cost of corrective action taken by the purchaser and chargeable to the supplier under the terms of the contract is:
a. payment authorization
b. bid cost considerations
c. release payment
d. back charge
e. none of the above.
ans: d
4. the sequential steps that define the process for successfully completing a project is:
a. implementation plan
b. a life cycle
c. development plan
d. a critical path
e. management plan來源:考試大
ans: b
5. which of the following time robbers end up creating additional work for the project manager and the project office?
a. failure to delegate
b. changes without notification or direction
c. unreasonable time constraints
d. over directing people
e. all of the above
ans: e
6. you are giving your team instructions on how to perform a new test which is different from the way that the team had performed it previously.
the best way to verify that the learn understands what you want is to:
a. obtain feedback
b. analyze the team's perceptions barriers
c. uses gestures in presenting the instructions
d. analyze the team's decoding skills
e. analyze the team's encoding skills來源:www.examda.com
ans: a
7. a common way by which executives provide the project manager with written authority is through:
a. a common job description for all project managers
b. an appointment letter
c. a project charter
d. all of the above
e. b and c only
ans: e
8. surveys have shown that the primary skill needed to be a project manager is communication skill. the typical project manager spends
approximately ______percent of his or her time communicating.
a. 40-50
b. 50-60
c. 60-75
d. 75-90
e. 90-95
ans: d
9. the work breakdown structure (wbs) is the basis for communicating:
a. project scope, cost control, schedule, quality
b. project objectives, dependencies, plan, cost control
c. project scope, schedule, staffing, cost control
d. project scope, quality, schedule, dependencies
e. project budget, schedule, risk factors, work assignments.
ans: a
10. the quality objectives are approved in the conceptual stage of the project by the:
a. project engineer
b. project manager
c. functional manager來源:www.examda.com
d. quality assurance manager
e. project owner
ans: e
11. total project risk:
a. should not be calculated for small projects
b. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the
project.
c. is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.
d. a and b
e. a and c
ans: c
12. _____ is a narrative description of the work to be accomplished or resource to be supplied.
a. purchase order
b. level of effort work
c. scope of work
d. contract stipulation
e. none of the above.
ans: c
本站推薦
- 1PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目一馬當(dāng)先?答案當(dāng)然是肯定的!
- 2項(xiàng)目進(jìn)度管理有難題?PMP系統(tǒng):一問就知,輕松解決
- 3PMP項(xiàng)目管理,項(xiàng)目進(jìn)度管理的疑問終結(jié)者,您還在等什么?
- 4項(xiàng)目進(jìn)度難掌控?PMP管理系統(tǒng):疑問解答,效率倍增!
- 5PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目效率翻倍?答案就在這里!
- 6項(xiàng)目進(jìn)度滯后?PMP管理系統(tǒng):一問就知道怎么加速!
- 7項(xiàng)目管理不再迷茫,PMP進(jìn)度系統(tǒng):您的疑問我來答
- 8PMP在手,項(xiàng)目進(jìn)度管理難題還用問嗎?輕松搞定
- 9還在為項(xiàng)目進(jìn)度頭疼?PMP管理系統(tǒng)幫您一問解千愁!