2010年P(guān)MP美國項目管理考試習題及答案32
QUEST In which of the following types of contracts is it most important for the contractor to maintain control of cost, schedule and scope changes.
A unit price
B cost plus incentive fee
C cost plus fixed fee
D firm fixed price
E B and D only
參考答案:D
QUEST In which of the following contract types is it easier to change the scope of the contract:
A firm fixed price
B fixed price plus incentive fee
C cost plus percentage of cost
D letter contract
E None of the above.
參考答案:C
QUEST Which of the following processes allow an unsuccessful bidder to seek remedy for contract award to another bidder.
A bid protest
B bid review
C award Protest
D award review
E any of the above processes can be used
參考答案:A
QUEST The "buy or make" decision is usually made during the:
A acquisition cycle
B contract evaluation cycle
C requirements cycle
D pre-award cycle
E at any time that is convenient for the project manager
參考答案:C
QUEST Back charges refers to:
A transferring charges from sub-contractors to the owner
B adjusting payments to reflect late invoices consequence
C the cost of corrective action taken by the owner and charged to the contractor for non-conformance
D gaining restitution from the owner for non payment
E C and D only
參考答案:C