2010年PMP美國項目管理考試習題及答案九十四
QUEST The following individuals are responsible for determining the content of the Communications Management Plan.
A Project Sponsor
B Task Manager(s)
C Director of Communications
D Project Manager
E參考答案:
參考答案:D
QUEST The Communications Management Plan should contain the following:
A Communications policy
B Communications media
C Reporting channels
D Selection of appropriate media to meet specific needs
E All of the above
參考答案:E
QUEST An effective Project Manager does not share project _____ with the team members.
A Vision
B responsibility
C solution to problems
D accountability
E status
參考答案:D
QUEST Using "I" or "My' instead of "most people" or "our group" ______ message credibility.
A decreases
B increases
C has no effect on
D distorts
E A and B
參考答案:B

QUEST The role of the _____ can be invaluable in problem solving.
A recognition seeker
B devils advocate
C dominator
D topic jumper
E A or C
參考答案:B