2010年PMP美國項目管理考試習題及答案七十七
QUEST Delegation may
A defer the decision on type of approach to be used.
B be interpreted as passive and uncaring
C tend to emphasize the task over the people involved.
D be frequently utilized by a project manager.
E All of the above.
參考答案:E
QUEST Japanese resource management models exhibit.
A a cooperative spirit of goal settings
B non-specialized career paths
C frequent changes on team assignments
D A and B.
E All of the above.
參考答案:E
QUEST Management by objectives assumes that the team
A is receptive to an unstructured environment.
B does not require close supervision
C possesses a self-fulfillment philosophy
D all of the above
E A and C
參考答案:C
QUEST The performance review interview is a vital component of any personnel evaluation system. Which of the following is not a characteristic of an effective personnel evaluation interview?
A Performed by a supervisor who has adequately prepared for the interview
B Discusses the employee's future performance goals
C Discusses the employee's undesirable personality traits
D Completed during a single, uninterrupted block of time
E Focuses on a limited number of topics so that each topic can be discussed in detail
參考答案:C
QUEST Management by Objectives (MBO)
A is a method used to evaluate personnel by objectively comparing them to common performance standards
B requires a supervisor and a subordinate to jointly establish performance objectives
C should be the responsibility of the organization's personnel department
D should always involve the establishment of objectives that are quantifiable
E B and D
參考答案:B