2010年P(guān)MP美國項目管理考試習(xí)題及答案四十七
QUEST Which of the following is considered a direct cost for producing a widget?
A The cost of the materials used to produce a widget.
B The labor costs of the workers who actually produced the widget.
C The rent for the building in which the widget was manufactured
D The salary of senior management and the project sponsor
E A and B only
參考答案:E
QUEST The reason that cost management is so difficult in project management is that:
A Projects by definition and nature are non-recurring events and are therefore difficult to predict.
B There are no tools for identifying project tasks.
C Project managers do not care about tracking costs, as only schedules are important to all project managers.
D A and B only
E B and C only
參考答案:A
QUEST Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:
A Baseline costs
B Budgeted costs.
C Estimates upon completion costs
D Scheduled costs
E None of the above
參考答案:A
QUEST The difference between the BCWS and the BCWP is referred to as the:
A Schedule variance
B Cost variance.
C Estimate of completion
D Actual cost of the work performed
E None of the above
參考答案:A
QUEST When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.
A Reduce features and/or functionality
B Increase risk.
C Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)
D All of the above.
E A and B only
參考答案:D