2010年PMP美國項目管理考試習題及答案六十一
QUEST Which of the following is not a cost of non-conformance?
A maintenance and calibration
B warranty repairs
C scrap
D rework
E All of the above.
參考答案:A
QUEST The cost of a quality program should be budgeted at _____ of the total project.
A 10-12%
B 2-3 %
C 6-8%
D 3-5%
E more than 15 %
參考答案:D
QUEST _____ of the extra costs of the project can often be attributed to a lack of quality.
A 12%
B 15%
C 20%
D 25%
E less than 10%
參考答案:C
QUEST CIP embodies which of the following principals?
A constancy of purpose
B customer focus and involvement
C total involvement
D teamwork
E All of the above.
參考答案:E
QUEST The key ingredient to a successful quality management program are _____.
A management's quality philosophy, operational quality assurance and operational quality control.
B quality evaluation methods and functional quality integrators.
C technical quality administration, the technical quality specifications, and the quality process review.
D quality evaluation methods, quality progress reviews and the technical quality specifications.
E All of the above.
參考答案:A