2010年P(guān)MP美國項目管理考試習題及答案四十六
QUEST Which of the following is referred to as payback period:
A the number of periods required to recover the initial investment
B the rate of return on the investment
C the number of periods required to bring project cost back to the original budget, based on current performance
D loan payment schedule
E None of the above
參考答案:A
QUEST Which of the following is referred to as sunk cost:
A management reserve
B contingency fund
C cost budgeted for construction under water
D expended funds over which there is no further control
E forecasted budget over-runs
參考答案:D
QUEST The future value of an annual income flow of $1000 for 2 years at 10% is:
A ¥2,200
B ¥2,280
C ¥2,300
D ¥2,310
E None of the above
參考答案:D
QUEST The net present value of $110 one year from now at 10% is:
A ¥100
B ¥120
C ¥121
D $100 less taxes
E $100 less taxes and interest
參考答案:A
QUEST Which of the following depreciation methods provides for accelerated depreciation of an asset:
A Double declining balance.
B Straight line.
C Exponential depreciation
D Double sum of the years digits
E Double increasing balance
參考答案:A