PMP美國項目管理模擬樣題3
been asked to perform a benefit/cost analysis for two proposed
projects. Project A costs $2.4 million with potential benefits of $12
million and future operating costs of $3 million. Project B costs
$2.8 million with potential benefits of $14 million and future
operating costs of $2 million. Which project should you recommend?
A. Project A because the cost to implement is cheaper than Project B
B. Project A because the potential benefits plus the future operating
costs are less in value than the same calculation for project B
C. Project B because the potential benefits minus the implementation
and future operating costs are greater in value than the same
calculation for Project A
D. Project B because the potential benefits minus the costs to
implement are greater in value than the same calculation for Project A
你是水路游艇公司的一名項目經(jīng)理。公司指派你對提議的兩個項目進行成本/收
益分析。項目A需要耗費的成本是240萬美元,潛在收益為1200萬美元,遠(yuǎn)期運營
成本為300萬美元。項目B需要耗費的成本是280萬美元,潛在收益為1400萬美
元,遠(yuǎn)期運營成本為200萬美元。你將向公司推薦哪個項目?
A. 項目A,因為其執(zhí)行成本比項目B少
B. 項目A,因為潛在收益加上遠(yuǎn)期運營成本的價值總額比項目B少
C. 項目B,因為潛在收益減去執(zhí)行成本和遠(yuǎn)期運營成本的價值額比項目A大
D. 項目B,因為潛在收益減去執(zhí)行成本的價值額比項目A大
2.You’ve been assigned as project manager on a research and
development project for a new dental procedure. You’ve published the
scope statement and are working on the scope management plan. What is
the purpose of the scope management plan?
A. It describes and documents a scope baseline to help make future
project decision.
B. It decomposes project deliverables.
C. It describes how project scope changes will be incorporated into
the project and how project scope will be managed.
D. It describes how cost and time estimates can be composed for
project scope changes.
你被任命為項目經(jīng)理,來負(fù)責(zé)研究和開發(fā)一項新的牙齒治療程序的項目。你已經(jīng)
發(fā)布了范圍說明書并正在準(zhǔn)備范圍管理計劃。請問,范圍管理計劃的目的是什么?
A. 它描述和說明的是一個范圍基準(zhǔn)以有助于未來的項目決策。
B. 它是對項目可交付成果的分解。
C. 它描述的是項目范圍變更將如何融入到整個項目中去,以及項目范圍將如何
管理。
D. 它描述的是項目范圍變更過程中成本和時間估算要如何調(diào)整應(yīng)對。
本站推薦
- 1PMP項目管理進度系統(tǒng),能否讓您的項目一馬當(dāng)先?答案當(dāng)然是肯定的!
- 2項目進度管理有難題?PMP系統(tǒng):一問就知,輕松解決
- 3PMP項目管理,項目進度管理的疑問終結(jié)者,您還在等什么?
- 4項目進度難掌控?PMP管理系統(tǒng):疑問解答,效率倍增!
- 5PMP項目管理進度系統(tǒng),能否讓您的項目效率翻倍?答案就在這里!
- 6項目進度滯后?PMP管理系統(tǒng):一問就知道怎么加速!
- 7項目管理不再迷茫,PMP進度系統(tǒng):您的疑問我來答
- 8PMP在手,項目進度管理難題還用問嗎?輕松搞定
- 9還在為項目進度頭疼?PMP管理系統(tǒng)幫您一問解千愁!