2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案七十六
申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114
QUEST The compromise conflict resolution technique
A is necessary when both participants must win.
B results in both sides losing
C is used when resolution is more important than relationships
D B and C
E All of the above.
參考答案:B
QUEST A life cycle project manager tends to have the following characteristics:
A balanced training
B stronger administrative skills than technical skills
C stronger technical skills than administrative skills
D stronger human resource skills
E None of the above.
參考答案:B
QUEST Which influence reflects an informal organization?
A formal authority
B reward power
C referent power
D expert power
E penalty
參考答案:C
QUEST The type of power most infrequently used by the PM is
A formal authority
B reward power
C referent power
D expert power
E penalty
參考答案:A
QUEST A key to successful Management by Objectives (MBO) is
A insuring that employees have clearly defined objectives
B involving employees in decision meetings
C permitting employees to set their own objectives
D allowing employees to perform their own evaluations
E A or C.
參考答案:E
相關(guān)試題:
2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案七十五
試題推薦:
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測
- 4交通部試驗(yàn)檢測師:交通安全設(shè)施測試題(2010年度)
- 5交通部試驗(yàn)檢測工程師:橋涵工程試驗(yàn)檢測試題(2010年度)
- 62010年公路工程試驗(yàn)檢測師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測師:公路、材料測試題(2010年度)
- 82010年一級(jí)建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國一級(jí)建造師執(zhí)業(yè)資格考試模擬試題(含答案)