QUEST The auditing function that provides feedback about the quality of output is referred to as:
A quality control.
B quality planning.
C quality assurance.
D quality improvement
E All of the above.
參考答案:C
QUEST Cost of quality is:
A associated with non-conformance to specifications and requirements.
B primarily caused by poor workmanship of workers who are building or manufacturing the product.
C used to determine whether a quality management program is suitable for a given project.
D negligible for most large projects.
E A and B
參考答案:A
QUEST Quality management:
A is another name for careful inspections.
B is inversely related to productivity.
C is primarily the responsiblity of management.
D is primarily the responsibility of the workers.
E is essentially a motivational technique.
參考答案:C
QUEST Quality may be defined as:
A conformance to requirements.
B fitness for use.
C continuous improvement of products and services
D appeal to the customer
E All of the above except B
參考答案:E
QUEST Using the scenario in the special window, the project manager appears to be a _____ manager.
A 1, 9
B 9, 1
C 1, 1
D 9, 9
E 5, 5
參考答案:E