2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案三十二
申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114
QUEST A network has been developed with resources from six different departments. One of the six departments has just informed you that they can increase the number of employees from 5 to 8. This will result in:
A A shortening of the critical path.
B A shortening of the noncritical path.
C A decrease in the total cost of the project.
D An increase in the cost of the project.
E A through D are possible based upon where the resources are deployed.
參考答案:E
QUEST Bar charts are most appropriate for:
A Comparing actual to planned performance to each activity.
B Showing slack time.
C Showing critical path dependencies.
D Showing which activities can be rearranged in parallel.
E All of the above.
參考答案:A
QUEST A non-critical path activity is completed in half the time. Then,
A The critical path is also reduced.
B The slack in the path containing this activity will increase.
C The total cost for this activity has decreased.
D Manpower from this activity can be assigned to other activities.
E All of the above.
參考答案:B
QUEST Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ .
A Slack for each activity, critical path.
B Slack for each activity, high risk activities.
C Manpower shortages, high risk activities.
D High risk activities, non-critical paths.
E Manpower availability, contingency plans.
參考答案:A
QUEST ADM is an activity-on-arrow method. In this method, a dummy activity:
A Denotes a critical path relationship.
B Denotes any dependency relationship.
C Shows slack.
D Identifies customer deliverables dates.
E Identifies customer team meeting dates.
參考答案:B
相關(guān)試題:
2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案三十一
試題推薦:
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測
- 4交通部試驗(yàn)檢測師:交通安全設(shè)施測試題(2010年度)
- 5交通部試驗(yàn)檢測工程師:橋涵工程試驗(yàn)檢測試題(2010年度)
- 62010年公路工程試驗(yàn)檢測師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測師:公路、材料測試題(2010年度)
- 82010年一級(jí)建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國一級(jí)建造師執(zhí)業(yè)資格考試模擬試題(含答案)