QUEST Scope management is:
A a project control function.
B employs change control.
C a work authorization process.
D considers Cost, Quality and Schedule.
E All of the above.
參考答案:E
QUEST Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?
A 5%
B 10%
C 15%
D 25%
E 50%
參考答案:D
QUEST Which of the following factors has historically been the greatest contributor to project failure?
A Planning performed by a planning group.
B Poor financial estimates.
C Lack of sufficient management reserve.
D Lack of management support.
E Not using an automated tracking tool.
參考答案:D
QUEST Which of the following planning considerations is often overlooked?
A Planning for project termination.
B Qualified project manager assignment.
C Insuring top management support.
D Clearly defined tasks.
E All of the above.
參考答案:A
QUEST The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.
A Conceptual
B Development.
C Execution
D Finish
E All of the above.
參考答案:E
相關(guān)試題:
2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案十五
試題推薦:
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測(cè)
- 4交通部試驗(yàn)檢測(cè)師:交通安全設(shè)施測(cè)試題(2010年度)
- 5交通部試驗(yàn)檢測(cè)工程師:橋涵工程試驗(yàn)檢測(cè)試題(2010年度)
- 62010年公路工程試驗(yàn)檢測(cè)師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測(cè)師:公路、材料測(cè)試題(2010年度)
- 82010年一級(jí)建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國(guó)一級(jí)建造師執(zhí)業(yè)資格考試模擬試題(含答案)