2010年P(guān)MP美國項目管理考試習(xí)題及答案二十八
QUEST On November 1, $1000 worth of work on task A was supposed to have been done (BCWS); however, the BCWP was $850. Calculate the schedule variance:
A ¥-100
B ¥100
C ¥-150
D ¥150
E 85%
參考答案:C
QUEST A plan has budgeted three weeks of effort for consultants, but the job was done in only two weeks. Calculate the variance:
A 1.50%
B 33.00%
C 75%
D 67%
E None of the above.
參考答案:B
QUEST Resource leveling will often affect the project by making it:
A Shorter.
B Longer
C More responsive to customer needs.
D A and C
E B and C.
參考答案:B
QUEST Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.
A 2
B 3
C 4
D 5
E 7
參考答案:C
QUEST Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.
A 2, 10
B 4, 12
C 6, 14
D 7, 15
E 9, 17
參考答案:A