成都公司:成都市成華區(qū)建設南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務大廈18樓
當前位置:工程項目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項目管理工具
2010年PMP美國項目管理考試習題及答案四十三
QUEST Using the situation stated in the Special window, what is the cost variance for Case #9?
A ¥-1,000
B ¥1,000
C -2000
D 2000
E 0
參考答案:B
QUEST Using the situation stated in the Special window, what is present value of $1000 at 12% at the end of 5 years?
A ¥3,605.00
B ¥0.57
C ¥567.00
D ¥892.86
E ¥3.61
參考答案:C
QUEST Using the situation stated in the Special window, what is net present value of an annual income flow of $1600 at 14% over the next three years?
A ¥3,713.60
B ¥0.68
C ¥1,080.00
D ¥476.19
E ¥2.32
參考答案:A
QUEST Using the situation stated in the Special window, what is the labor rate cost variance?
A ¥5,500.00
B ¥1,500.00
C ¥-100.00
D ¥-0.10
E ¥5,600.00
參考答案:D
QUEST Using the situation stated in the Special window, what is the total price variance for direct material?
A ¥140.00
B ¥736.00
C ¥0.02
D ¥-350.00
E ¥5,850.00
參考答案:B
相關試題:
2010年PMP美國項目管理考試習題及答案四十二
試題推薦:
2010年PMP美國項目管理認定考試全真模擬試題精選1
2010年PMP美國項目管理認定考試全真模擬試題精選2
2010年PMP美國項目管理認定考試全真模擬試題精選3