2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案四十二
申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114
QUEST Using the situation stated in the Special window, what is the cost performance index for Case #9?
A 1.1
B 1.91
C 0.83
D 1.2
E None of the above
參考答案:A
QUEST Sunk costs are:
A future costs held in reserve.
B costs invested in commodities.
C expended costs over which we have no control.
D expended costs over which we have no more control
E tax credits
參考答案:D
QUEST Managerial Reserves are:
A allowances to account for price changes that can occur over the life of a project.
B incentive fees paid to managers for good performance.
C funds used to offset poor cost or schedule estimates.
D accounts to allocate and maintain funds for contingency programs
E All of the above.
參考答案:D
QUEST Life Cycle Costing:
A is the concept of including all costs within the total life of a project.
B is an activity devoted to optimizing cost/performance
C is an activity of appraising the cost and technical performance of a completed project.
D is a process of predicting the life of a project.
E None of the above.
參考答案:A
QUEST Using the situation stated in the Special window, what is the schedule variance for Case #8?
A 1000
B 2000
C -1000
D -2000
E 0
參考答案:C
相關(guān)試題:
2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案四十一
試題推薦:
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測(cè)
- 4交通部試驗(yàn)檢測(cè)師:交通安全設(shè)施測(cè)試題(2010年度)
- 5交通部試驗(yàn)檢測(cè)工程師:橋涵工程試驗(yàn)檢測(cè)試題(2010年度)
- 62010年公路工程試驗(yàn)檢測(cè)師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測(cè)師:公路、材料測(cè)試題(2010年度)
- 82010年一級(jí)建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國一級(jí)建造師執(zhí)業(yè)資格考試模擬試題(含答案)