QUEST The salvage value of an asset is:
A The value of the scrap metal if a new asset were taken to a scrap yard.
B The value that an asset has on the books after one year of depreciation.
C The costs that have been sunk into the project to date.
D The expected cash value at the end of an assets useful life.
E A and D only.
參考答案:D
QUEST The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:
A Multiplying the actual hours worked on the project by the budgeted labor rate.
B Multiplying the budgeted hours to complete the task by the budgeted labor rate.
C Dividing the actual hours required to complete the task by the budgeted labor rate.
D Cannot be determined.
E None of the above
參考答案:B
QUEST The methods and techniques for determining the economic costs, the environmental impact, the economic returns, and the probability for success are called:
A Feasibility studies.
B Bills of materials.
C Pert charts.
D Managerial reserves.
E None of the above
參考答案:A
QUEST The planned cost for the total project at its inception is called the _____.
A Cost of goods sold.
B Depreciable value.
C Budgeted cost.
D All of the above.
E B and C only.
參考答案:C
QUEST Which of the following is not a measure of the profitability of a project or program?
A Return on original investment.
B Net present value.
C Depreciation.
D Discounted cash flow.
E None of the above
參考答案:C