2010年P(guān)MP美國項目管理考試習(xí)題及答案四十九
QUEST Typically, during which phase in a project life cycle are most of the project expenses incurred.
A Concept phase
B Development of design phase
C Execution phase.
D Termination phase.
E None of the above
參考答案:C
QUEST What tool have project managers come to use to identify all of the costs associated with a project.
A A bill of materials
B A Gantt chart
C An arrow diagram network.
D A work breakdown structure.
E B and C only.
參考答案:D
QUEST You must produce 27 widgets. You can only produce 9 widgets per production run. Each production line setup costs $1000. Each widget consumes $10 worth of material and $5 worth of labor. What is total variable cost for producing one widget.
A ¥1,020
B ¥1,010
C ¥1,015
D ¥20
E None of the above
參考答案:E
QUEST You must produce 27 widgets. You can only produce 9 widgets per production run. Each production line setup costs $1000. Each widget consumes $10 worth of material and $5 worth of labor. What is the total fixed cost for producing the widgets.
A ¥3,000
B ¥27,000
C ¥27,270
D ¥1,335
E ¥1,000
參考答案:E
QUEST In a contract, the point of total assumption refers to the point where:
A The customer incurs the total financial responsibility for each additional dollar spent.
B The contractor incurs the total financial responsiblity for each dollar spent.
C The schedule and cost variance are zero.
D The customer will incur no further costs for the work the contractor performs in the completion of the contract.
E B and D only.
參考答案:E