2010年P(guān)MP美國項目管理考試習(xí)題及答案三十六
QUEST In the PDM, common constraints include:
A Start-to-start
B Finish-to-start
C Finish-to-finish
D B and C only
E A, B, and C.
參考答案:E
QUEST Activities with zero time duration are referred to as:
A Critical path activites.
B Noncritical path activities.
C Slack time activities.
D Dummies
E None of above.
參考答案:D
QUEST In the arrow diagramming method (ADM), _____ do not consume time or resources.
A Events.
B Activities
C Slack elements.
D B and C only.
E All of the above.
參考答案:A
QUEST On a precedence diagram, the arrow between two boxes is called:
A An activity.
B A constraint.
C An event.
D The critical path.
E None of above.
參考答案:B
QUEST A project element which lies between two events is called:
A An activity.
B A critical path method.
C A slack milestone.
D A timing slot.
E A calendar completion point.
參考答案:A