2010年P(guān)MP美國項目管理考試習(xí)題及答案三十七
QUEST The basic terminology for networks includes:
A Activities, events, manpower, skill levels and slack.
B Activities, documentation, events, manpower and skill levels.
C Slack, activities, events, and time estimates.
D Time estimates, slack, sponsorship involvement, and activities.
E Time estimates, slack time, report writing, life cycle phases, and crashing times.
參考答案:C
QUEST The utility of network-based schedules:
A Reveals interdependencies.
B Facilitates "what if" exercises.
C Highlights critical activities.
D Provides information on resource requirements, time requirements and tradeoffs.
E All of the above.
參考答案:E
QUEST The major disadvantage of a bar chart is:
A Lack of time-phasing.
B Cannot be related to calendar dates.
C does not show activity interrelationships.
D Cannot be related to manpower planning.
E Cannot be related to cost estimates.
參考答案:C
QUEST The most common types of schedules are Gantt charts, milestone charts, line of balance, and:
A Networks.
B Time phased events.
C Calendar integrated activities.
D A and C only.
E B and C only.
參考答案:A

QUEST Scheduling is the process by which decisions are made concerning:
A Tasks to be accomplished.
B Personnel/organization that will be assigned to accomplish the task.
C Time when the tasks are to be completed.
D All of the above.
E A and C only.
參考答案:E