2010年P(guān)MP美國項目管理考試習(xí)題及答案二十一
QUEST The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:
A Work packages.
B Subtasks.
C Tasks.
D Code of accounts.
E Integration points.
參考答案:C
QUEST A task-oriented family tree of activities is a:
A Detailed plan.
B Linear responsibility chart.
C Work breakdown structure.
D Cost account coding system.
E Work package description.
參考答案:C
QUEST Management plans include all of the following except:
A Organization of project.
B Job descriptions.
C Policies and procedures.
D Linear responsibility charts.
E Scope baseline.
參考答案:E
QUEST A comprehensive definition of scope management would be:
A Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.
B Approval of the scope baseline.
C Approval of the detailed project charter.
D Configuration control.
E Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.
參考答案:A
QUEST The process of choosing/documenting the best approach to achieve the project objectives is part of:
A The scope baseline.
B Scope authorization
C Scope definition
D Scope planning.
E All of the above.
參考答案:D