QUEST Configuration (baseline) control monitors performance against the
A scope baseline
B original schedule
C original budget
D All of the above.
E None of the above.
參考答案:A
QUEST A summary WBS is usually developed in the
A Conceptual phase
B implementation phase
C planning phase
D close-out phase
E All of the above phases
參考答案:A
QUEST A project may be defined as _____
A an integrated approach to managing projects
B a coordinated undertaking of interrelated activities.
C a group of activities directed by a project manger over a life cycle
D an undertaking with a defined starting point and defined objectives
E All of the above.
參考答案:D
QUEST Approval to proceed is normally made at the end of the _____ phase of a typical project.
A conceptual
B development
C implementation
D execution
E close-out
參考答案:A
QUEST Lessons learned are most often based upon project historical records. Lessons learned can be used to:
A See what mistakes others have made
B See how others have solved problems
C Predict trends, highlight problems and identify alternatives
D All of the above
E A and B only
參考答案:D
試題推薦:
2010年PMP美國項目管理考試習題及答案一
2010年PMP美國項目管理考試習題及答案二
2010年PMP美國項目管理考試習題及答案三
2010年PMP美國項目管理考試習題及答案四
2010年PMP美國項目管理考試習題及答案五
2010年PMP美國項目管理考試習題及答案六
2010年PMP美國項目管理考試習題及答案七
2010年PMP美國項目管理認定考試全真模擬試題精選1
2010年PMP美國項目管理認定考試全真模擬試題精選2
2010年PMP美國項目管理認定考試全真模擬試題精選3